W.P. Hickman Lead Times for Architectural Edge Metal

Taking advantage of Hickman's lean manufacturing strategy which accelerates production schedules, the reduced lead times apply to Hickman's entire line of standard and custom-order products, as indicated in the following table:

Standard W.P. Hickman Co. Products Lead Time
Prefinished (Standard colors) with folded or metal-lock accessories 7 working days
Prefinished (Standard colors) with up to 30 welded accessories 10 working days
Post-finished with non-exotic Kynar colors 15 working days
Radius/arched coping 15 working days
Pre-finished with more than 30 welded accessories 15 working days
Post-finished with exotic or metallic Kynar colors or Post-finished anodizing 20 working days


For custom-developed products, add five working days to standard product lead times.

In 2007 products were shipped within standard lead times 96.6% of the time.